While one person is holding up the Column, the other one should level it vertically on both lateral
sides and on the front.
5.
Anchor the Wall Support to the wall.
6.
Perform the leveling adjustments on Column Base and on the Column Upper Support. Make sure
that the Column is correctly leveled and firmly tighten. Anchor the Column Base to the floor.
7.
Place the Control Box on its final position of the room, keep in mind:
•
The length of the Column Harness (approx. 1.5m - 59”) that goes from the Column to the
Control Box.
•
The length of the High Voltage Cables (X-Ray Tube HV Transformer in the Generator
Cabinet).
•
The Swivel Arm movements.
8.
Level the Control Box using the Adjustable Leveling Legs. Keep the Base at the maximum distance
from the floor.
9.
Usually the Generator Cabinet is installed on top of the Control Box. (Make sure to run the 5’ J5
to Generator cable for positioned sync)
10.
Leave a working area around the Generator Cabinet until its final installation.
11.
Perform the corresponding connections from the Column (Main Harness) in the Control Box.
12.
Remove the Positioner Control (Monitor) from the Support of the Tube Collimator Support, for
that, unscrew the four fixing screws and carefully leave it resting on the Carriage Arm.