Commissioning
Mount the FP1 B carefully according to the steps described in chapter 5.2.
Depending on the scope of delivery, you must also carry out the following additional
measures for the first-time commissioning:
1. Mechanical fastening
Fix the FP1 B mechanically through the M5 female threads or through the M16 male
thread of the FP1 B lubricant outlet. Pay particular attention to the maximum tightening
torques permissible for the M5 female threads!
2. Check the assembly
Make sure that the FP1 B is properly and completely assembled. In particular, the bat-
tery must be inserted and a lubricant cartridge must be fitted.
3. Power on
If you want to put the FP1 B into operation, switch on the FP1 B. Only if you switch on
the FP1 B, it delivers lubricant to the lubrication point according to the settings. The
detailed description for powering on can be found in chapter 6.3.3.
4. Execute FIL function
Execute the FIL function. The detailed description can be found in chapter 6.3.10. FP1
B performs a certain number of strokes and transports the lubricant from the cartridge
to the outlet.
5. Hydraulic connection
Connect the consumer hydraulically to the FP1 B. If you connect tubes to the FP1 B,
make sure that the tubes and connectors are installed tightly, cleanly and correctly.
Ideally, use tubes prefilled with the appropriate lubricant!
6. Check the settings on FP1 B
Check the factory settings of FP1 B with the required values for the lubrication point
and adjust them if necessary. The factory settings are recorded in chapter
at the FP1 B must be made in the SET-Menu, chapter. 6.3.6, and in the PRO-Menu,