Chapter 3 Termination board wiring
28
BMTK-SVN01D-EN
Wire the utility pulse meter
Wire the utility pulse meter to the termination board input.
1.
Route input wires into the termination module through a conduit
opening (Figure 12 on page 19) or the conduit box.
2.
Connect the wires to the METER INPUT terminals on the termina-
tion board (Figure 14 on page 24).
3.
Connect the other end of the wires to the pulsed-output contacts of
the electrical meter.
Wire the thermistor
The thermistor input is for a Trane outdoor air temperature sensor only.
The input cannot be used for any other purpose. Using wire that meets
the specifications listed in Table 6 on page 26, wire the thermistor to the
termination board input.
1.
Route input wires into the termination module through a conduit
opening (Figure 12 on page 19) or the conduit box.
2.
Connect the wires to the THERMISTOR terminals on the termination
board (Figure 14 on page 24).
3.
Connect the shield to the ground terminal.
4.
Connect the other end of the wires to the thermistor device.
IMPORTANT
Tape the shield at the sensor. Any connection between the shield and
ground will cause a malfunction.
Note:
The thermistor input is not polarity sensitive.
Содержание Tracker Version 12
Страница 1: ...BMTK SVN01D EN Hardware Installation Tracker Version 12 Building Automation System...
Страница 2: ......
Страница 3: ...Hardware Installation Tracker Version 12 Building Automation System BMTK SVN01D EN February 2004...
Страница 4: ......
Страница 30: ...Chapter 2 Termination module mounting 22 BMTK SVN01D EN...
Страница 48: ...Chapter 3 Termination board wiring 40 BMTK SVN01D EN...
Страница 52: ...Chapter 5 Display module mounting 44 BMTK SVN01D EN Figure 22 Tab and slot alignment...
Страница 53: ...Display module mounting BMTK SVN01D EN 45 Figure 23 Display module engagement...
Страница 54: ...Chapter 5 Display module mounting 46 BMTK SVN01D EN...
Страница 70: ...Chapter 7 Troubleshooting 62 BMTK SVN01D EN...
Страница 72: ...Chapter 8 Maintenance 64 BMTK SVN01D EN...
Страница 80: ...Appendix A Installation checklists 72 BMTK SVN01D EN...
Страница 87: ......