CNT-SVX12C-EN
37
Chapter 6
Sequence of operations for
the 4-cool configuration
A Tracer ZN517 unitary controller configured to control a 4-cool unit will
operate to maintain the zone temperature setpoint. This chapter dis-
cusses many of the operational sequences the controller uses to accom-
plish this goal.
Power-up sequence
When 24 Vac power is initially applied to the Tracer ZN517 unitary con-
troller, the following sequence occurs:
1.
The Status (green) LED goes on.
2.
All outputs are controlled off.
3.
The controller reads all input local values to determine initial values.
4.
The power-up control wait function begins automatically if the config-
ured power-up control wait time is greater than zero. When this func-
tion is enabled, the controller waits for the configured amount of time
(from 10 to 120 seconds) to allow a communicated occupancy request
to arrive. If a communicated occupancy request arrives, normal oper-
ation can begin. If a communicated occupancy request does not arrive,
the controller assumes stand-alone operation.
5.
The Status LED goes off.
6.
The wait timer expires.
7.
The Status LED goes on.
8.
If a hard-wired zone-temperature value is not detected, the controller
begins to wait for a communicated value. (This can take several min-
utes [15-minute default] and occurs concurrently with the remainder
of the power-up sequence.) If a communicated zone-temperature
value arrives, normal operation can begin when the power-up
sequence has concluded. If a communicated zone-temperature value
does not arrive, the binary outputs remain off and a Space Tempera-
ture Failure diagnostic is generated (normal operation cannot begin
without a valid zone temperature value).
9.
Normal operation begins assuming no diagnostics have been gener-
ated.
Содержание Tracer ZN517
Страница 1: ...CNT SVX12C EN Installation and Operation Tracer ZN517 Unitary Controller...
Страница 2: ......
Страница 3: ...Installation and Operation Tracer ZN517 Unitary Controller CNT SVX12C EN April 2005...
Страница 4: ......
Страница 12: ...Table of contents vi CNT SVX12C EN...
Страница 38: ...Chapter 4 Sequence of operations for the 2 heat 2 cool configuration 26 CNT SVX12C EN...
Страница 56: ...Chapter 6 Sequence of operations for the 4 cool configuration 44 CNT SVX12C EN...
Страница 92: ...Chapter 10 Status indicators for operation and communication 80 CNT SVX12C EN...
Страница 104: ...Chapter 12 Troubleshooting 92 CNT SVX12C EN...
Страница 110: ...Index 98 CNT SVX12C EN...