26 |
P a g e
Tigo Energy, Inc.
|
www.tigoenergy.com
|
Torque Table
Table 6 Torque table
EI Battery front cover (
9
)
1.0Nm
Inverter connection wire box (
8
)
1.0Nm
Battery expansion wire box (
12
)
1.0Nm
Mounting anchors
1.0Nm
BAT-Expansion terminals
1.0Nm
BAT-INV terminals
1.0Nm
Powering on the EI Solution
Warning
!
Before powering on this system, ensure the appropriate PPE is being used,
including insulated tools.
Note:
All other components of the EI Battery Storage system, including the energy
meter must be installed for the system to operate.
1.
Turn ON the disconnect switch (
4
) above the
Inverter connection wire box
(
8
).
2.
If multiple batteries installed, turn on the BAT-Expansion breaker in the Battery expansion
wire box (
12
). Otherwise, skip this step.
3.
Turn on the inverter and wait 10 seconds for the inverter to send the wake-up signal.
Observing the LED indicator of the battery enclosure, confirm the battery system enters the
discharge state (center leaf is lit green). The battery storage system has been successfully
started.
4.
Use the EI mobile app to commission the system. Set the battery to charge to >60%.
Note:
All grid settings, modes of operation, and communications
preferences take place in the Energy Intelligence App. This
communication occurs between the mobile device and the EI
Inverter. The inverter communicates all settings/modes of operation
to the EI Battery.