cOMMIssIONINg
43
© TESVOLT We reserve the right to make technical changes. Version RD.TI.015.E.ENG_Installation_Manual_TS48V_v.C.01 Last revised 06/2020
6
The number of battery modules detected is shown on the display.
Confirm the number is correct by tapping twice on the marking
14
next to the display. If the displayed number of modules differs from
the number actually present, switch the APU off and check the
BAT-COM wiring.
If the fault continues to occur regardless, please contact the
TESVOLT Service Line +49 (0) 3491 87 97 - 200 or email to
[email protected].
7
The TS 48 V now switches to “INIT” mode and the switch starts to
flash.
Once initialization has been successfully completed and a fault-
free status is achieved, the APU automatically begins the pre-
charging process “PRECH”.
After pre-charge mode, the switch lights up permanently. The
status point on the battery display reads “OK”. The TS 48 V is now
operational.
8
Tap beside the display again to access the next menu item. You
will now be shown the assigned IP address, provided the LAN
connection
8
is connected to the APU by a DHCP enabled router.
9
Next, commission the SMA Sunny Island System in accordance with the SMA specifications.
NOTE:
The APU display remains active for approximately two minutes and is then deactivated. It can
be reactivated by tapping twice.
Depending on the number of modules installed, the storage capacity in ampere hours can be taken
from the table and entered at the corresponding menu point when commissioning the Sunny Island(s).
STORAGE CAPACITY AS A FUNCTION OF THE NUMBER OF BATTERY MODULES
Number of battery modules
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Capacity (Ah)
94
188
282
376
470
564
658
752
846
940
1034 1128 1222 1316 1410 1504
Table 8.1. Storage capacity as a function of the number of battery modules