INsTAllATION
27
© TESVOLT We reserve the right to make technical changes. Version RD.TI.015.E.ENG_Installation_Manual_TS48V_v.C.01 Last revised 06/2020
13
TS cabinet only:
Ground the cabinet door with the grounding
strip
J
. Use the grounding point on the side panel a few centi-
meters above the base, roughly at the same height as the lowest
door hinge. First, remove the protective caps from the copper
bolts on this grounding point and the cabinet door. Then connect
the two grounding points using the grounding strip and the M8
nuts
J.1
with washer
J.2
and contact washer
J.3
. The tighten-
ing torque is 10 Nm.
14
TS cabinet only:
Install the C-rail
B
above the APU position. To
do this, first, take the auxiliary tool and install two cage nuts
E
in the two rack rails in the fourth hole from the top
E.1
. Fasten
the C-rail to these with two M6 x 16 pan head screws
D
(Phil-
lips) and two plastic washers
D.1
.
TS 25 only:
The APU has to be installed first due to the TS 25
cabinet’s small dimensions. The C-rail can then be fitted.
15
Prepare the base for fitting the storage system. A brush strip can
be used in the base of the cabinet for easy cable routing. Simply
install the brush strip on the required side of the base. To relo-
cate the brush strip, two screws must be removed on the right
and left sides of the brush strip. Then remove the base cover
plate on the relevant side of the cabinet. Swap the brush strip and
cover plate and then refit both.
16
The base cover plates
C
/
C.1
can now be fitted. The cover
plates are snapped into place on each corner of the cabinet base.
The logo on each base cover plate must face forwards on the
front of the cabinet and to the rear on the back of the cabinet
6.2 FITTING A CABINET EXTENSION
1
The first step is to remove the side panels on each cabinet where
the cabinets are to be connected together.