Operating Instructions
24
1096.0799 | VU / VH Series
10/2010
9.
Disassembly of mechanical seal (SU 1/2) (
Preparations
for assembly, page 26)
Push the stationary units of the mechanical seals
(047/047.1) out of the shaft sealing casings (441).
10. Disassembly of inter casing of the suction/discharge casing
Loosen the hexagon socket head screw (914) in the
suction/discharge casing (106/107).
Remove the inter casing (137/137.3) from the suc-
tion/discharge casing (106/107).
Additional steps for VH 110/140/180
Separate the central inter casings (137.1/137.2).
Remove the packing gland (461) from the inter
casing (137.1).
7.5.6 Disassembly of VU 300/450,
VH 300/350/400
Cross-sectional drawing VU 300/450
Cross-sectional drawing, page 54
Cross-sectional drawing VH 300/350/400
Cross-sectional drawing, page 60
The pump has been removed from the system and is stored
in a clean and level assembly area.
1.
Disassembly of pipes (not applicable to VU 300)
Loosen the hexagon nuts (920), remove the pipes
(700) with hexagon head screws (901) and seals
(400.1).
2.
Disassembly of bearing housing on suction casing (drive
side)
Remove the fitting key (940.1) from the pump shaft
(211).
Loosen the hexagon head screws (901.3), pull the
bearing housing (330) with the rolling bearing (320) off
the pump shaft (211).
Pull off the splash ring (507).
3.
Disassembly of mechanical seal (RU 1) (
Preparations for
assembly, page 26)
Loosen the hexagon head screws (901.2), pull the
shaft sealing casing (441) and the rotating unit of the
mechanical seal (047) off the pump shaft (211).
Pull off the spacer sleeve (525).
4.
Disassembly of bearing housing on discharge casing (non-
drive side)
Loosen the hexagon head screws (901.1), pull the
bearing cover (360.1) off the pump shaft (211).
Loosen the lock washer (931.1) and the shaft nut (921)
and pull them off.
Additional steps for VU 300/450
Pull the ring (500) off the pump shaft (211).
Loosen and pull off the withdrawal sleeve (531) by
tightening the supplied shaft nut (921.1).
Loosen the screws (901.3), pull the bearing housing
(330) with the rolling bearing (320.1) and the ring
(500.1) off the pump shaft (211).
Pull off the splash ring (507).
5.
Disassembly of mechanical seal (RU 1) (
Preparations for
assembly, page 26)
Loosen the hexagon head screws (901.2), pull the
shaft sealing casing (441) and the rotating unit of the
mechanical seal (047.1) off the pump shaft (211).
Pull off the spacer sleeve (525).
6.
Disassembly of suction casing
Rotate the pump 90° (drive side pointing up).
Loosen the nuts (920/920.1), remove the nuts and the
casing bolts (563).
Remove the suction casing (106).
7.
Disassembly of stage casing and pump shaft
Remove the stage casing (110).
Remove the pump shaft (211) with the impeller (230).
With VH 300/350/400
Remove the pump shaft (211) with the inter cas-
ings (137.1/137.2) and impellers (230/230.1).
Remove the stage casing (110.1).
8.
Disassembly of impeller and pump shaft
Loosen and remove the shaft nut (922) and the lock
washer (931) at the drive side.
Pull the impeller (230) off the shaft.
Additional steps for VH 300/350/400
Remove the fitting key (940) from the pump shaft
(211).
Pull the inter casings (137.1/137.2) jointly off the
shaft protection sleeve (523).
Pull the impeller (230.1) and the shaft protection
seal (523) off the pump shaft (211).
Pull the fitting key (940.1), the lock washer (931) and
the impeller nut (922) off the pump shaft (211).
9.
Disassembly of mechanical seal (SU 1/2) (
Preparations
for assembly, page 26)
Push the stationary units of the mechanical seal
(047/047.1) out of the shaft sealing casings (441).
10. Disassembly of inter casing of the suction/discharge casing
Loosen the hexagon socket head screw (900/900.1) on
the suction/discharge casing (106/107).
Remove the inter casing (137/137.3) from the suc-
tion/discharge casing (106/107).
Additional steps for VH 300/350/400
Separate the central inter casings (137.2/137.1).
11. Disassembly of valve flaps
Not applicable to VH 300/350/400
VU 450 inter casings (137/137.3)
VU 300 inter casing (137.3)
Loosen the hexagon head screws (901.5) on the inter
casing (137/137.3).
Remove the stop plate (598/598.1) and the flap valve
(746).
7.5.7 Disassembly of VU 351/451
Cross-sectional drawing VU 351/451
Cross-sectional
drawing, page 58
The pump has been removed from the system and is stored
in a clean and level assembly area.
1.
Disassembly of pipes
Loosen the hexagon nuts (920.1), remove the pipes
(700), the hexagon head screws (901) and the seals
(400).
2.
Disassembly of bearing housing on suction casing (drive
side)
Remove the fitting key (940) from the pump shaft
(211).
Loosen the hexagon head screws (901.3), pull the
bearing housing (330) with the rolling bearing (320) off
the pump shaft.
Pull off the splash ring.
3.
Disassembly of mechanical seal (RU 1)
Loosen the hexagon head screws (901.3), pull the
shaft sealing casing (441) and the rotating unit of the
mechanical seal (047) off the pump shaft.