Step 10:
Press the gun onto the workpiece at an angle of 90 degrees.
When using a contact gun, press it firmly
against the spring force.
Step 11:
Push the release button of the gun.
Welding is carried out.
During the welding process, hold the gun steadily and only remove
it vertically from the welded stud after the welding process is
finished. By doing so, widening or damaging the stud chuck is
avoided.
The welding process is finished
.
After removing the welding gun or welding head from the welded stud, a welding stud
is reloaded into the gun or head. After a few seconds, the system is ready to weld
again (LED "Ready" lights up).
8.1.1
Refilling the feeder during operation
To refill the feeder, open the protective hood (this switches off the compressed-air
supply) and pour the welding studs directly into the feeder bowl. Observe the permitted
filling weight and that the stud type matches.
Afterwards, mount the protective hood. The compressed-air supply is re-established
and work can be continued.
8.2
Switching off the universal feeder
Switch off the universal feeder at the mains switch.
Switch off the main compressed air or disconnect the device from the compressed-air
supply.