Location
Clearance
Indoor Installation
Outdoor Installation
Locations where the
annual average high
temperature
(1)
is
below 25˚C / 77˚F
20 cm / 8"
between inverters
5 cm / 2" between
inverters (if inverters are
also installed one above
the other, maintain the
indoor installation
clearance)
Locations where the
annual average high
temperature
1
is
above 25˚C / 77˚F
40 cm / 16"
between inverters
3. If you are
not
using the level:
Position the mounting brackets against the wall and mark the required drilling
holes locations. The distance between neighboring holes from different brackets
should be 9 cm / 3-5/8"
Figure 14 to ensure a distance of 1.2" (3 cm) between
inverter units.
NOTE
Make sure to maintain the required distance between brackets and units,
otherwise the cables connecting the Secondary Unit(s) to the Connection
Unit may not reach the connectors.
(1)
Annual average high temperature – the average of the 12 monthly average highs,
for example:
to find the value in your location.
-
Three Phase Inverter with Synergy Technology Installation MAN-01-00402-1.2
30
Mounting and Connecting the Primary and Secondary Unit(s)