Step 4:
Lock in place all cable connection kits by using ¼” Tapcon® bolts to secure them into the concrete floor in the 3
locations - through the shims (if they are present). Refer to Tapcon® for proper pilot hole sizes.
Figure 45. Cable connection kits locking
Step 5:
Proceed with the wiring of the DC cables, the internal Ethernet communication and the battery communication
cables and chiller and auxiliaries power supply cables. All these cables are supplied with the system.
Start from the C-Cab and connect the batteries from the nearest to the furthest. The details of the electrical connections will
be found in the Electrical installation chapter.
Dimensions
in
/mm
188
7.4
Ø
0.79
Ø20
Ø6.8
Ø
0.27
Ø
0.23
Ø5.8
86
3.49
Batteries
+
grounding
Auxiliaries
+
CAN
Figure 46. Cables organization inside the cable gutter
Содержание SUNSYS HES L
Страница 1: ...SUNSYS HES L USER MANUAL Energy Storage System EN UL...
Страница 5: ...SUNSYS HES L 551697A SOCOMEC 5 EN...
Страница 15: ...SUNSYS HES L 551697A SOCOMEC 15 EN CHILLER SWITCHES BATTERY MODULES Figure 02 SUNSYS B Cab L composition...
Страница 114: ...551697A CORPORATE HQ CONTACT SOCOMEC SAS 1 4 RUE DE WESTHOUSE 67235 BENFELD FRANCE www socomec com...