NETYS RT 5 - 7 - 9 - 11 kVA - 551570A - SOCOMEC
62
EN
For example, if you need to execute a battery test, please go to Test
→
Start
Battery Test
→
Test In Progress…
→
Test Result: Pass (or Fail).
Start Battery Test
Deep Discharge Test
Local Dry Contact test
Test
Battery Aging
Reset
Log
1/2
- Test
Battery Test
Test In Progress...
Battery
272.0V
Press ESC key to abort test
85%
Battery Test
Test In Progress...
Battery
272.0V
Press ESC key to abort test
85%
Battery Test
Test In Progress...
Battery
272.0V
Press ESC key to abort test
85%
ESC
ESC
ESC
Test Completed