8 Initial Commissioning
8.1 Requirements
The Quick Configuration Guide (QCG) allows you to quickly install and commission your off-grid
system. To do so, use the menu to select the 'right' system for you. The display then shows a selection
via which the parameters can be set specifically.
Check the connections
Before starting the commissioning process, make sure all electrical connections have the
correct polarity and are connected according to the instructions.
Always save data
Always use the SD card to save data and events. In case of a failure SMA Solar
Technology can thus quickly help you.
Содержание SI 5048
Страница 1: ...SI5048 TEN093630 TBE SI5048 Version 3 0 EN Off grid Inverter SUNNY ISLAND 5048 Technical Description...
Страница 2: ......
Страница 10: ...Table of Contents SMA Solar Technology AG 10 SI5048 TEN093630 Technical Description...
Страница 43: ...SMA Solar Technology AG Electrical Connection Technical Description SI5048 TEN093630 43...
Страница 66: ...Operation SMA Solar Technology AG 66 SI5048 TEN093630 Technical Description Overview of the menu structure...
Страница 209: ......
Страница 210: ......
Страница 212: ...4 4PMBS 5FDIOPMPHZ XXX 4 EF...