SMA Solar Technology AG
Multicluster Operation
Technical Description
SI5048-TEN093630
127
Proceed as follows when connecting the communication cable:
Proceed as follows to implement the connection:
1. Remove the left of the two plugs in the rubber terminal area.
2. Feed the RJ45 cable from the outside through the plugs inside the Sunny Island master.
3. Plug the RJ45 plug in the lower socket. The termination resistor remains plugged in the upper
one.
4. Lead the RJ45 cable into the next Sunny Island and connect it to the upper socket there.
5. Insert the termination resistor into the lower socket if no other Sunny Island will be connected.
6. Wrap the rubber plug (depending on the number of cables with one or two feed-throughs)
around the RJ45 cable.
7. Reinsert the plugs in the opening provided in the rubber terminal area.
Содержание SI 5048
Страница 1: ...SI5048 TEN093630 TBE SI5048 Version 3 0 EN Off grid Inverter SUNNY ISLAND 5048 Technical Description...
Страница 2: ......
Страница 10: ...Table of Contents SMA Solar Technology AG 10 SI5048 TEN093630 Technical Description...
Страница 43: ...SMA Solar Technology AG Electrical Connection Technical Description SI5048 TEN093630 43...
Страница 66: ...Operation SMA Solar Technology AG 66 SI5048 TEN093630 Technical Description Overview of the menu structure...
Страница 209: ......
Страница 210: ......
Страница 212: ...4 4PMBS 5FDIOPMPHZ XXX 4 EF...