Assembling and Installing Systems
A-7
Automation System S7-400 Hardware and Installation
A5E00850741-01
Five Basic Rules for Ensuring Electromagnetic Compatibility
In many cases, you can ensure electromagnetic compatibility by observing the
following five basic rules:
Rule 1: Large Area Grounding
When installing the programmable controllers, provide large-area good quality
grounding of the inactive metal parts (see Section A.3).
•
Make a large-area low-impedance connection of all inactive metal parts to
chassis ground.
•
For screw connections on painted or anodized metal parts, either use special
contact washers or remove the insulating protective layers from the contact
points.
•
If possible, do not use aluminum parts for grounding. Aluminum oxidizes easily
and is therefore less suitable for grounding.
•
Make a central connection between chassis ground and the ground/protective
ground conductor system.
Rule 2: Correct Cable Routing
Ensure proper routing of lines when wiring (see Sections A.7 and A.8).
•
Arrange the cabling in line groups (AC power cables, power supply cables,
signal lines, data lines).
•
Always install AC power cables and signal or data lines in separate ducts or
bunches.
•
Route the signal and data lines as closely as possible to grounded surfaces
such as cabinet elements, metal bars and cabinet panels.
Rule 3: Secure Cable Shields
Ensure that cable shields are properly secured (see Section 4.9).
•
Only use shielded data lines. The shield must have a large-area connection to
ground at each end.
•
Analog lines must always be shielded. For the transfer of signals with low
amplitudes, it may be advisable to connect the shield to ground at only one end.
•
Provide the line shields with a large-area connection to a shield/protective
ground bar immediately after the cabinet inlet, and secure the shields with cable
clamps. Route the grounded shield as far as the module without interruption, but
do not ground it there again.
•
There must be a low-impedance connection between shield/protective ground
bar and cabinet/housing.
•
Use metal or metallized connector cases for shielded data lines.
Содержание Simatic S7-400
Страница 6: ...Preface vi Automation System S7 400 Hardware and Installation A5E00850741 01 ...
Страница 52: ...Installing the S7 400 2 36 Automation System S7 400 Hardware and Installation A5E00850741 01 ...
Страница 60: ...Addressing the S7 400 3 8 Automation System S7 400 Hardware and Installation A5E00850741 01 ...
Страница 128: ...Networking 5 30 Automation System S7 400 Hardware and Installation A5E00850741 01 ...
Страница 148: ...Commissioning 6 20 Automation System S7 400 Hardware and Installation A5E00850741 01 ...
Страница 228: ...Index Index 4 Automation System S7 400 Hardware and Installation A5E00850741 01 ...