To start the run and view its progress, follow the steps below:
1.
Tap
Next
in the
Load the tip rack
step. The
Run setup selection overview
dialog is shown.
Figure 119. Run setup selection overview dialog.
2.
If all the information in the overview is correct, tap
Start
to immediately proceed with the
protocol run. To make modifications to any of the selections, tap
Return
to go back to the run
setup.
Note
: The
Estimated run time
does not include the time to complete the
Load Check,
which is
approximately 6 minutes.
3.
If the hood of the instrument is open, close it and the run will start.