[ Table 8-1 : LED Indications ]
[ Figure 8-1 : LCD Location ]
[ Figure 8-2 : Initial Indication Screen on Power On ]
[ Figure 8-3 : Update Screen ]
Solar (A)
Battery (B)
Grid (C)
OFF
Green
Red
Energy is not being generated.
Energy is being generated.
Fault
Battery is not connected.
Battery is connected.
Fault
Grid is not connected.
Grid is connected.
Fault
69
I
Operating Test
8.2.1 Loading Screen & Update Screen
The [Figure 8-2] is displayed at the time of initial boot, and the home screen is displayed when
internal communication is normal. The time setting is automatically renewed when connected
to the network. The [Figure 8-3] is a screen display when ESS Software (PMS & PCS) is updated.
8. Operating Test
8.1 LED Indications
As shown in the [Figure 8-1], the LED of Q.HOME
+
ESS HYB-G2 is located at bottom of LCD.
The color of LED depend on current status of INVERTER and LED display information can be checked
in [Table 8-1].
8.2 Starting the System
After completing the installation, turn on the AC circuit breaker installed in the distribution box and then
turn on the DC disconnect switch on the product.
Check the system check message on the front LCD screen.
A
B
C