The pasteurizer must be positioned so that rear
part is at least
20 cm
from walls or any object,
thereby permitting free air circulation.
Block the wheels with supplied brakes. It is
advisable to leave a space between the sides of
the machine and surrounding walls, thereby
facilitating cleaning operations.
A 17 - INSTALLATION
A 18 - USE OF MACHINE
A 18.1 OPERATION START-UP
cm 40
O F F
A 18.5 - MACHINE PREPARATION
For STARMIX 120 models the wall switch must be
turned on at least
4/5
hours before beginning work.
This permits the resistance inserted in the motor-
driven compressor body to heat the oil contained
therein, thereby avoiding the breakage of the
compressor due to a cold start-up.
It is advisable that first work cycle following machine
installation is carried out with cylinder full of water
rather than mix, in order to control the various cycle
work phases.
To carry out above, proceed as follows:
A 18.2
Open the tap of water
mains (
62
).
A 18.3
Connect to mains with
relative switch (
37
)
especially provided for
during installation.
A 18.4
O
n the display, the sign U20 will apprear for 2
seconds. This sign identifies the version of the
software. After that the word OFF will appear.
- Check that OFF is written on display
- Lift the lid and pour water into the cylinder for a quantity
not lower than advised minimal values reported in
technical specifications.
- Press button (
28
) and the temperature of the water in
the cylinder will appear on display.
- Press button (A) or (B) and the cycle will begin.
- Complete the cycle, empty the cylinder through the
extraction cock.
- Close the front half-cover.