55
Installation Manual
been configured.
3. Setting Procedures
3-1. Setting Procedures
The following settings and test runs are required in order to start up this system normally;
● The actual operation cannot be performed until all the settings have
● Turn off the DC protector the protection device for the storage battery system, and the protection device for
Network Adaptor.
[1] Checking Energization
•
Turn ON the DC protector and the protection
device and check that the power is supplied
normally.
(See chapter 4)
[2] Setting Date/Time
•
Set the date/time in order to activate the clock
function.
(See chapter 5)
[3] Setting Parameters
•
Set the operation parameters.
(See chapter 6 and 7)
[4] Test Runs
•
•
•
Perform test runs such as the reverse current
Check battery lot number status.(See chapter 9)
Check PCS communication status.
(it connecting three PCS) (See chapter 9)
CT test and stand-alone operation test.
(See chapter 8)
[5] Checking Network Adaptor Connections
•
Turn ON and launch the Network Adaptor
and check the communications between the
Network Adaptor and the storage battery
system.
(See chapter 9)
2. Setting Date/Time
3. Setting Parameters
4. Test Runs
5. Checking the Network Adaptor
Connections
1. Checking Energization
Starting Settings
Completing Settings
for five seconds and then return to normal state.
4-2. Powering ON the DC/AC
● The work must be performed by qualified personnel.
After finishing the wiring, check that the battery system side wiring and the GRID connection were normally completed
4. Checking Energization
4-1. Checking Energization
in accordance with installation instructions and local regulations.
● Check that the wiring work has been completed in accordance with Chapter "Installation".
The device may fail if the power is turned on with it incorrectly wired.
■
Preparation
•
Check that the wiring work has been completed in accordance with Chapter "Installation".
•
Set the protection device for the Network Adaptor to OFF. (
)
■
Operation Procedure
CT
CT
L
N1
N
L1
COM
COM
SYS
PE
PE
PE
Switch board
N
L
PE
N
Stand-alone
Socket-outlet
(Type-02)
Turn off these protection
devices in an emergency.
Network
Adaptor
Main
switch
Point of
Supply
TN or TT
system
Storage
battery
system
DC Protector
DC Protector
SB
SB
2
SB
1
SB
1
•
Turn ON the DC Protector.
(
)
Power is supplied from the battery to the system.
All indicator LED lamps illuminate
All LED lamps illuminate for five seconds and then return to normal state.
• Turn ON the protection device for the storage battery system.(
) Power is supplied from the AC side to the system.
DRED
Protection
device for
Storage
battery
system
Protection
device for
Network
Adaptor