12 Commissioning
PCS-9611 Feeder Relay
12-18
Date: 2014-04-08
2. De-energize all the binary inputs of this relay.
3. Simulate a normal condition with normal currents and the circuit breaker is closed.
4. Simulate a abnormal condition, make all three phase currents be less than the setting
[37.I_Set] and make the circuit breaker be closed.
5. After the period of [37.t_Op], the undercurrent protection will operate and issue the trip
command. The “
TRIP
” LED indicator will be on; a relevant report will be shown on the LCD.
6. After the fault is disappeared, this relay will restore the undercurrent protection automatically.
Restore the “
TRIP
” indicator and the LCD manually.
12.5.4 On-load Checks
The objectives of the on-load checks are:
Confirm the external wiring to the current and voltage inputs is correct.
Measure the magnitude of on-load current and voltage (if applicable).
Check the polarity of each current transformer.
However, these checks can only be carried out if there are no restrictions preventing the
tenderization of the plant being protected.
Remove all test leads, temporary shorting leads, etc. and replace any external wiring that has
been removed to allow testing.
If it has been necessary to disconnect any of the external wiring from the protec tion in order to
perform any of the foregoing tests, it should be ensured that all connections are replaced in
accordance with the relevant external connection or scheme diagram. Confirm current and voltage
transformer wiring.
12.5.4.1 Final Checks
After the above tests are completed, remove all test or temporary shorting leads, etc. If it has been
necessary to disconnect any of the external wiring from the protection in order to perform the
wiring verification tests, it should be ensured that all connections are re placed in accordance with
the relevant external connection or scheme diagram.
Ensure that the protection has been restored to service.
If the protection is in a new installation or the circuit breaker has just been maintained, the circuit
breaker maintenance and current counters should be zero. If a test block is installed, remove the
test plug and replace the cover so that the protection is put into service.
Ensure that all event records, fault records, disturbance records and alarms have been cleared
and
LED’s has been reset before leaving the protection.
Содержание PCS-9611
Страница 1: ...PCS 9611 Feeder Relay Instruction Manual NR Electric Co Ltd...
Страница 2: ......
Страница 10: ...1 Introduction PCS 9611 Feeder Relay 1 b Date 2014 04 08...
Страница 30: ...2 Technical Data PCS 9611 Feeder Relay 2 14 Date 2014 04 08...
Страница 36: ...3 Operation Theory PCS 9611 Feeder Relay 3 f Date 2014 04 08...
Страница 108: ...4 Supervision PCS 9611 Feeder Relay 4 b Date 2014 04 08...
Страница 116: ...5 Management Function PCS 9611 Feeder Relay 5 b Date 2014 04 08...
Страница 120: ...5 Management Function PCS 9611 Feeder Relay 5 4 Date 2014 04 08...
Страница 218: ...9 Configurable Function PCS 9611 Feeder Relay 9 b Date 2014 04 08...
Страница 232: ...9 Configurable Function PCS 9611 Feeder Relay 9 14 Date 2014 04 08...
Страница 262: ...11 Installation PCS 9611 Feeder Relay 11 b Date 2014 04 08...
Страница 272: ...12 Commissioning PCS 9611 Feeder Relay 12 b Date 2014 04 08...
Страница 292: ...13 Maintenance PCS 9611 Feeder Relay 13 b Date 2014 04 08...
Страница 296: ...14 Decommissioning and Disposal PCS 9611 Feeder Relay 14 b Date 2014 04 08...
Страница 298: ...14 Decommissioning and Disposal PCS 9611 Feeder Relay 14 2 Date 2014 04 08...
Страница 300: ...15 Manual Version History PCS 9611 Feeder Relay 15 2 Date 2014 04 08...