Follow-up Procedure
After connecting cables, reinstall the covers of the power distribution subrack, rear
panel, and side panel of the bypass cabinet.
After connecting cables, check that a certain clearance is reserved between the internal
switch (if any) extension pole and power cables to avoid friction.
3.2.5.2 Bottom Cabling
Context
Install cables for the UPS from inside out and from bottom up.
After routing cables, use firestop putty to seal the gaps between the cables and the
cabinets.
Procedure
Step 1
Open the front door of the cabinet, and remove the front cover of the power distribution
subrack from the bypass cabinet.
Step 2
Remove the cable covers from the bottom of the cabinet, drill holes in the covers, attach
grommet strips to the hole edges for protecting cables, and reinstall the cable covers.
The hole diameter and quantity are for reference only.