FusionModule5000 Smart Modular Data Center
Commissioning Guide
6 Commissioning the Management System
Issue 06 (2020-03-20)
Copyright © Huawei Technologies Co., Ltd.
81
Figure 6-23
Adding an ECC800 device to the modular
Click
OK
, and you can view the task information, including
Type
,
Device Name
,
Region
,
Progress
,
Status
,
Start Time
,
End Time
, and
Information
in the displayed
Progress
window.
During binding of the ECC800 for the first time, the screen will be locked indefinitely when the
progress bar reaches 30%, and displays
Loading device profile. Please try it later.
The actual
operation results prevail.
6.6.5 Video Management
6.6.5.1 Networking Scenarios
Smart ETH Gateway Networking Scenario
There are multiple VCNs for multiple smart modules, you are advised to evenly
distribute the cameras to each VCN.
A maximum of four cameras can be connected in the smart ETH gateway networking
scenario.
Figure 6-24
VCN connecting to the ETH gateway