FusionModule5000 Smart Modular Data Center
Commissioning Guide
5 Commissioning the Cooling System
Issue 06 (2020-03-20)
Copyright © Huawei Technologies Co., Ltd.
25
5
Commissioning the Cooling System
5.1 Power-On
Procedure
Step 1
Turn on the smart cooling product switch in the power distribution cabinet and the AC1 and
AC2 switches on the smart cooling product.
Step 2
After the system is powered on for the first time, the
Quick Settings
screen is displayed. Log
in as the admin user, as shown in
Figure 5-1
Initial power-on
Table 5-1
Preset password
User
Preset Password
Permission Description
admin (administrator
user)
000001
People can operate all menus.
operator (common
user)
000001
People can only view parameter settings
and set a part of parameters in the
menus.