77
4000511390
E03.16 USA
/
GB
General datal
Pins and bearing inspection
MS0002
General datal
Pins and bearing inspection
1 - You will need
2 - Preliminary operation
The operations of disassembling if they exist should be carried out only on the installations completely disconnected
and must be entrusted only to people having the necessary technical training.
Respect, in addition to the instructions appearing in the present instructions, the legal tendencies generally applicable
for safety accident prevention.
All the precautions must be done in work before intervening on and near the machine.
After completion of work, all the covers and safety devices must be positioned back completely and operational.
3 - Control and maintenance
The control of pins, stop pins, bushes and bearing must be carried out according to the following recommendations :
•
Every day before use
: Fast visual inspection without disassembling.
• Check the presence of the pins and visible stops pins without disassembling.
• Check the presence of the screws.
• Check absence of deformations, cracks or breakage of pins and/or stops pins.
• Check absence of heavy abrasion, wear or oxidation of the pins, stops pins.
•
All 250 h or 6 months
: Reinforced visual inspection with disassembling of certain elements to reach the bushes
or bearing. In addition to the above cited criteria, verify the following :
• Check the presence and the position of the bushes and bearings.
• Check the absence of shaving in periphery of the pins.
• Check the absence of heavy abrasion, wear or oxidation of the bushes and bearing.
• Check the absence of deformations, cracks or breakage of the bushes and bearing.
• Check the absence of radial gap > 0,5 mm (19690 µ in) on the pins.
• Standard tool kit
• Protective goggles
• Gloves
• Place barriers around the perimeter of the work area
Exclusively use tools and auxiliary average adapted. Always wear necessary safety clothing.
Содержание HT21RT O
Страница 86: ...86 4000511390 E03 16 USA GB General data Breaking test procedure MS0004 Notes...
Страница 94: ...94 4000511390 E03 16 USA GB Chassis and turntable Tires Tyres and pressures Wheel replacement MS0006 Notes...
Страница 106: ...106 4000511390 E03 16 USA GB Chassis and turntable Gearbox inspection Oil replacement MS0011 Notes...
Страница 132: ...132 4000511390 E03 16 USA GB Chassis and turntable KUBOTA diesel engine MS0029 Notes...
Страница 142: ...142 4000511390 E03 16 USA GB Chassis and turntable Overload system MS0017 Notes...
Страница 160: ...160 4000511390 E03 16 USA GB Chassis and turntable Dismantling Reassembling wheels reducer MS0026 Notes...
Страница 184: ...184 4000511390 E03 16 USA GB Upper boom Procedure of dismantling reassembling telescope cylinder MS0014 Notes...
Страница 188: ...188 4000511390 E03 16 USA GB Upper boom Boom adjustment procedure MS0015 Notes...
Страница 192: ...192 4000511390 E03 16 USA GB Upper boom Boom angle sensor adjustment MS0018 Notes...
Страница 222: ...222 4000511390 E03 16 USA GB Hydraulics Hydraulic oil Level Replacement MS0019 Notes...
Страница 231: ...231 4000511390 E03 16 USA GB Hydraulics Hydraulic ways MS0023 F o l i o 2 2...
Страница 233: ...233 4000511390 E03 16 USA GB Hydraulics Hydraulic ways MS0023 F o l i o 2 2...
Страница 235: ...235 4000511390 E03 16 USA GB Hydraulics Hydraulic ways MS0023 F o l i o 2 2...
Страница 237: ...237 4000511390 E03 16 USA GB Hydraulics Hydraulic ways MS0023 F o l i o 2 2...
Страница 239: ...239 4000511390 E03 16 USA GB Hydraulics Hydraulic ways MS0023 7 Jib...
Страница 240: ...240 4000511390 E03 16 USA GB Hydraulics Hydraulic ways MS0023 Notes...
Страница 242: ...242 4000511390 E03 16 USA GB Electric Electrical wiring MS0025 Notes...