Unpacking Inspection
1.Indoor unit: nitrogen is sealed during the delivery of indoor units (inside the evaporator), and the red sign at the
top of the green plastic seal cap on the evaporator air pipes of the indoor unit shall be checked first after unpacking.
In case the sign is raised, the nitrogen sealed still exists. Afterwards, the black plastic seal cap at the joint of
evaporator liquid pipes of the indoor unit shall be pressed, to check whether nitrogen still exists. In case no nitrogen
is sprayed out, the indoor unit is subject to leakage, and installation is not allowed.
2.Outdoor unit: the leak detection equipment shall be extended into the packing box of the outdoor unit, to check
whether the refrigerant is leaking. If the refrigerant leakage is identified, installation is not allowed, and the outdoor
unit shall be delivered to the maintenance department.
Inspection on Installation Environment
1.Inspection on the surrounding environment of place of installation: the outdoor unit of flammable refrigerants air
conditioner cannot be installed inside an enclosed room reserved.
2.Power supply, switches or other high-temperature articles such as the fire source and oil heater shall be avoided
below the indoor unit.
3.The power supply shall be provided with earthing wire and be reliably earthed.
4.While punching the wall with an electric drill, whether embedded water/electricity/gas pipelines are designed at
the hole preset by the user shall be verified in advance. It is recommended that the through-wall holes reserved
shall be used as much as possible
Safety Principles of Installation
1. Favorable ventilation shall be maintained at the place of installation (doors and windows are opened).
2. Open fire or high-temperature heat source (including welding, smoking and oven) higher than 548 is not
allowed within the scope of flammable refrigerant.
3. Anti-static measures shall be taken, such as the wearing of cotton clothes and cotton gloves.
4. The place of installation shall be convenient for installation or maintenance. Barriers shall be avoided around the
air inlet/outlet of the indoor/outdoor unit, and the electrical appliance, power switches, sockets, valuables and high-
temperature products within the scope of both sidelines of the indoor unit shall be avoided, and cannot be adjacent
to heat source and flammable and combustible environment.
5. In case the product is damaged, it must be delivered to the maintenance point. Welding of refrigerant pipelines at
the user's site is not allowed.
Electrical Safety Requirements
1.The surrounding conditions (ambient temperature, direct sunlight and rainwater) shall be noticed during electrical
wiring, with effective protective measures being taken.
2.Copper wire cable in line with local standards shall be used as the power line and connector wire.
3.Outdoor unit shall be reliably earthed.
4.The dedicated branch circuit must be used, and leakage protector with sufficient capacity must be installed.
Qualification Requirements of Installer
Relevant qualification certificate must be obtained as per national laws and regulations.
Outdoor Unit Installation
Fixing and connection
Note:
a) Fire source shall be avoided within 3m around the place of installation.
b) The leak detection equipment of refrigerant shall be placed at a low position in the
outdoor, and shall be opened.
Caution, risk of fire
No Smoking
Cotton clothes
Anti-static gloves
BEWARE
ELECTROSTATICS
Goggles
Содержание HU062WAMNA
Страница 1: ...ATW Split Service Manual SYJS 2022 A Edition 2022 A ...
Страница 16: ...16 6 Piping Diagram ...
Страница 25: ...25 Cooling Tao C Two C Ta Ambient temperature Two Outlet water temperature ...
Страница 79: ...79 No Drawing Name of parts Quantity 1 Drainage elbow 4 2 Rubber cushion 4 Accessories ...