GST200-2 Intelligent Fire Alarm Control Panel
Installation and Operation Manual
Page 15
Chapter 4 Installation
The steps below are guidance for installation of the FACP.
1
Check if you have received all items ordered.
2
Install the cabinet.
3
Power up the FACP and carry out start-up inspection.
4
Connect field devices.
5
Inspect circuits and register devices.
6
Define devices and C&E equations on a PC and download them to the FACP
through definition software according to engineering configuration.
7
Commission and inspect field devices.
4.1 Component Inspection
Before installation, check the following items:
Check Engineering Requirement
Check the components according to packing list. The main items to be examined are:
installation and operation manual, keys to the FACP, etc.
Check Internal Components and Interconnection of the FACP
All internal parts have been connected (including optional units ordered) before the
FACP leaves the factory. Therefore, you can mainly check the zone indication and
manual intervention panel and power supply, and the connection among parts, including
the connection between main board and power supply, switch board and loop interface
board, the connection of the zone indication and manual intervention panel with switch
board, and of speaker and main board etc. Please refer to Appendix 1 for the internal
connection diagram.
4.2 Installing the Cabinet
Dimension of the cabinet is shown in Fig. 4-1.
Ambient conditions for installation of the FACP:
Temperature: 0
℃
~
+
40
℃
Relative humidity
≤
95
%
, non-condensing