Leveling the Discharge Chutes
Before You Begin
When testing the chute positions, the damper switch must be depressed when the cover is removed
before the system can function. Use tape to secure the damper switch in the depressed position.
What You Should Know
The chain is connected to a cable with a turnbuckle. The cable travels up the outside of the bin to the
chute pulley on the bin eave and goes through the sidewall sheet into the bin to the center collar and
down to the lift plate. The lift plate is connected to the chutes with chains. The chute controller retracts the
cable to close the chutes or extends the cable to open the chutes.
1. Use the turnbuckle to adjust the chutes until they are horizontally level for the closed position.
2. Position the chutes to the open position and verify that the chutes fully open.
3. Visually verify that the sprocket goes through a full open to close rotation by performing the limit
switch test.
4. When all adjustments have been made, secure the front chain guard cover to the chute controller
mount.
5. Install the enclosure cover (A) and secure with 5/16 x 3/4 in. flange bolts (B).
Figure 9-7
Attaching the enclosure cover
A
Enclosure cover (TD-101330)
B
5/16 x 3/4 in. flange bolt (S-6606)
114
PNEG-4936
36 Ft. TopDry Autoflow
Содержание TopDry Autoflow
Страница 6: ...NOTES 6 PNEG 4936 36 Ft TopDry Autoflow...
Страница 26: ...NOTES 26 PNEG 4936 36 Ft TopDry Autoflow...
Страница 46: ...NOTES 46 PNEG 4936 36 Ft TopDry Autoflow...
Страница 106: ...NOTES 106 PNEG 4936 36 Ft TopDry Autoflow...
Страница 128: ...NOTES 128 PNEG 4936 36 Ft TopDry Autoflow...
Страница 140: ...NOTES 140 PNEG 4936 36 Ft TopDry Autoflow...