5. Align the holes along the edge of the next top panel (E) with the holes of the previously installed top
panel.
6. Install the flange bolts (F) and flange nuts (G), securing the two top panels (E) together with the
center collar channel bracket (C).
NOTE:
Make sure to check the threads on the weld nuts.
Figure 8-35
Installing the adjacent top panel
C
Center collar channel brackets (CTR-1580)
F
3/8 x 1 in. flange bolt with sealing washer (S-
7487)
D
Inner center collar (CTR-1581)
G
3/8 in. flange nut (S-9426)
E
Top panel (CTR-1585)
7. Continue installing the remaining center collar flashing until the gap between the outer and inner
center collars is covered.
NOTE:
Remember to remove the flange bolts from the first top panel before placing rope caulk
between the overlap of the first and the last panels.
8. Tighten all the hardware to the recommended specifications. See
Bolt Torque Specifications, page
.
132
PNEG-4472
72 Ft Diameter Z-Tek Bins
Содержание 40-SERIES
Страница 6: ...NOTES 6 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 18: ...NOTES 18 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 26: ...NOTES 26 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 34: ...NOTES 34 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 72: ...NOTES 72 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 168: ...NOTES 168 PNEG 4472 72 Ft Diameter Z Tek Bins ...