Assembling the Lower Stand-off Bracket to the Outer Center Collar
There are eight lower stand-off support brackets that need to be assembled to the outer center collar
before it is lifted onto the roof with the center pole.
Before You Begin
For this procedure, the outer center collar needs to sit securely on stands or suitable blocks.
1. Locate a set of four holes on the top of the outer center collar (A) and place the lower stand-off sup-
port bracket (B).
2. Install the flange bolts (C) and flange nuts (D) to secure the lower stand-off support bracket (B) with
the outer center collar (A).
3. Repeat the procedure to continue installing all the remaining lower stand-off brackets (B) to the
outer center collar.
4. Tighten all the hardware to the recommended specifications. See
Bolt Torque Specifications, page
.
Figure 8-16
Assembling the lower stand-off brackets
A
Outer center collar (CTR-1603)
C
3/8 x 1-1/2 in. bolt (S-7488)
B
Lower stand-off support bracket (CTR-1559)
D
3/8 in. flange nut (S-9426)
112
PNEG-4472
72 Ft Diameter Z-Tek Bins
Содержание 40-SERIES
Страница 6: ...NOTES 6 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 18: ...NOTES 18 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 26: ...NOTES 26 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 34: ...NOTES 34 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 72: ...NOTES 72 PNEG 4472 72 Ft Diameter Z Tek Bins ...
Страница 168: ...NOTES 168 PNEG 4472 72 Ft Diameter Z Tek Bins ...