Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial INSTALLATION
53
1.3.4 Pipe connection
1.3.4.1 Flaring connection
The refrigerant pipes and IDUs are connected by using the flare opening. Therefore, the quality of
flaring connection must be ensured. The flaring depth of the bell mouth cannot be smaller than the
caliber. The flaring direction must face towards the direction of medium flow. Use two torque wrenches to
fasten the connection.
1.3.4.2 Socket welding
The gap between socket components should be proper to ensure that the connection will not loose
from the friction surface. The flaring direction of the socket component must face towards the direction of
medium flow .During pipe connect, protect the braze welding part according the length specified below:
A: External Diameter of the Pipe
B: Minimum Insertion Depth
D-A: Gap between Pipes
mm
inch
mm
inch
mm
inch
6.35
1/4
6
0.24
0.05-0.21
0.002-0.008
9.52
3/8
7
0.28
12.7
1/2
15.8
5/8
8
0.32
0.05-0.27
0.002-0.01
19.05
3/4
10
0.39
22.2
7/8
25.4
1
28.6
1-1/8
12
0.47
0.05-0.30
0.002-0.012
31.8
1-1/4
38.1
1-1/2
19
0.75
0.15-0.35
0.006-0.014
44.5
1-3/4
1.3.4.3 Bell socket welding
The bell socket welding is another form of socket welding. It uses the sleeve or pipe in a larger size
for welding. The insertion depth cannot be smaller than that required by socket welding.
1.3.4.4 Flange connection
The pipes with large caliber and the devices are always connected by using a flange, which must be
clean and intact. Before installation, apply lubricant on the surface of the flange. Two flanges must be
symmetrical. Fasten with screws at the diagonal direction to avoid inclination.
1.3.5 Welding protection
Aerate with nitrogen before and during welding and keep aerating for 30s after the welding is
finished.
Equip a pressure regulator valve to the nitrogen cylinder.
Содержание Ultra Heat GMV-VQ72W/A-F
Страница 1: ...Ultra Heat GMV Multi VRF TECHNICAL SERVICE MANUAL R410A Heat Recovery Series ...
Страница 26: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial INSTALLATION 22 CHAPTER 2 INSTALLATION ...
Страница 30: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial INSTALLATION 26 ...
Страница 73: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial INSTALLATION 69 ...
Страница 120: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 116 CHAPTER 4 MAINTENANCE ...
Страница 135: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 131 ...
Страница 136: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 132 2 System high pressure protection E1 ...
Страница 137: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 133 3 System low pressure protection E3 ...
Страница 167: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 163 PFC board Drive board ...
Страница 203: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 199 5 4 NCHS4B U ...
Страница 205: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 201 5 5 NCHS8B U ...
Страница 207: ...Jf00303410 ...