MDE-3985L Encore® Installation Manual · May 2006
Page 31
Installation
Anchoring Pump/Dispenser to Island
Note: Pumps do not normally require shear valves. The following procedure for a pump is
identical to a dispenser, except the shear valve may not be used.
1
Verify shear valves are firmly anchored to island form (concrete or pit box). See
Figure 3-15
.
Note: If shear valve is not properly anchored it may not operate correctly during a severe
impact. Follow shear valve manufacturer instructions.
Figure 3-15: Anchoring Shear Valve using Anchor Brackets
2
Loosely anchor the pump/dispenser to the island per foundation layout locations and using all
required anchoring points according to the following:
Use 1/2-inch anchor studs with heavy duty large washers (slot designed for that size)
Use bolts or studs that are grade 5 steel.
Use hardware that is corrosion protected or resistant.
Note: Do not use plastic or low strength bolts, or pallet bolts
Studs/bolts must be securely anchored to the island or pit box. See
Figure 3-16.
See anchor or pit box manufacturer instructions for additional important information.
WARNING
Improper anchoring of units could cause damage, server injury or death resulting from unit tipping
over from impact or drive off.
NFPA 30A requires anchoring pumps/dispensers.
Securely install anchor bolts at all anchoring locations as shown on foundation diagrams for safe
operation of shear valves and hose breakaways.
Pump/dispenser
base
Anchor
bracket