GEDA
®
3700 Z/ZP
Assembly
ML034 GB 2017 / 11
Page 49 of 60
Assembly Instructions
6.9
Assembling the cable carriage and central feeder (optional)
The cable box is only designed for a flat cable of approx. 50 m. Installation
up to the assembly height is carried out as previously described. For
assembly heights of more than 50 m, the travelling cable must be
extended and guided by a central feeder and cable carriage.
6.9.1
Installing the cable carriage
The cable carriage is installed when the platform is a minimum of 3 m
above the ground.
To install the cable carriage, a minimum of two mast sections must
be assembled on the base mast (refer to Chapter6.7.1).
DANGER
Danger to life
Crushing by the platform.
Never remain inside the cordoned-off area during operation.
Use the ground control and move the platform upwards to approx.
3 metres above the ground.
Push the setting mechanism into the right base mast (see maintenance
manual).
Remove the counter
roller (5) from the
cable carriage (4).
Insert the cable
carriage (4) on the
mast in the direction of
the arrow.
Install the counter
roller (5) on the cable
carriage (4).
Place the cable roller (6) on the shaft of the cable carriage (4), align
vertical and firmly attach with screws.
5
5
4
4
6