ZP3 Fire Control Panel Installation, Commissioning and Maintenance Manual
Page 40
REV 11 (ISS 08/03/2010)
Surface mounting
Figure 33 illustrates the main requirements for surface mounting of the ZP3 panel.
Figure 33: Surface mounting
Use appropriate mounting screws such as plastic rawl plugs, expansion anchors, etc. depending
on the type of wall. Use M4 screws at least 20 mm long. The mounting system must be able to
support a minimum weight of 20 kg, which is the total weight of the panel (with batteries).
Содержание ZP3
Страница 1: ...GE Security ZP3 Fire Control Panel Installation Commissioning and Maintenance Manual ...
Страница 44: ...ZP3 Fire Control Panel Installation Commissioning and Maintenance Manual Page 32 REV 11 ISS 08 03 2010 ...
Страница 56: ...ZP3 Fire Control Panel Installation Commissioning and Maintenance Manual Page 44 REV 11 ISS 08 03 2010 ...
Страница 142: ...ZP3 Fire Control Panel Installation Commissioning and Maintenance Manual Page 130 REV 11 ISS 08 03 2010 ...
Страница 143: ...ZP3 Fire Control Panel Installation Commissioning and Maintenance Manual REV 11 ISS 08 03 2010 Page 131 ...
Страница 144: ...ZP3 Fire Control Panel Installation Commissioning and Maintenance Manual Page 132 REV 11 ISS 08 03 2010 ...