CHAPTER 4
ETSI Configuration
Installing Power and Ground Cables
4-67
FLASHWAVE 7500 Release 6.1
Equipment Installation
Fujitsu and Fujitsu Customer Use Only
FNC-7500-0061-200
Issue 1, May 2009
Disconnect Power from PDP
2
If installing into a powered rack, disconnect office power (recommended) or remove fuses
from the PDP.
3
Use a DMM to ensure 0 V DC (with reference to the battery ground) at the point of
disconnection.
Install Shelf Power Harnesses A1 and B1
4
Identify the shelf that is to be connected to buses A1 and B1.
5
Locate the rack/shelf power harnesses (PC660-0105-T019 and PC660-0105-T020,
) for the shelf.
Note:
The length of the cables may be altered at the discretion of the installer to ensure proper
length.
6
Prepare the power leads by installing the terminal lugs that are required on one end of the
cable (see
). Ensure that no wire strands are shorting terminals together
and that leads are securely fastened. The cable should now have terminal lugs on both ends of
the power cable.
Note:
The shelf power wiring is the same with all rack configurations. Observe the color coding of the
power cable.
7
On the station interface area (SIA) of the shelf identified in
, remove the
plastic covers on the shelf power terminal strips located on the bottom left and bottom right
of the SIA (see
8
Connect both ends of cable GA of the power harness as follows:
a.
Identify lug GA in the power harness (see
) and connect it to shelf
terminal GA (see
b.
Connect the other end of the same cable to PDP terminal A1-1 +RTN (see
).
Revision 1, June 2009
Содержание FLASHWAVE 7500
Страница 8: ...Revision 1 June 2009 ...
Страница 10: ...Revision 1 June 2009 ...
Страница 16: ...Revision 1 June 2009 ...
Страница 362: ...Revision 1 June 2009 ...
Страница 386: ...Revision 1 June 2009 ...