CHAPTER 3
Small Configuration
Installing the 19-Inch (SFD5) DCM Shelf
3-61
FLASHWAVE 7500 Release 6.1
Equipment Installation
Fujitsu and Fujitsu Customer Use Only
FNC-7500-0061-200
Issue 1, May 2009
shows a right-side view of the SFD5 shelf after the flange is mounted.
12
Install the DCM shelf in the bottom of the rack. Secure the shelf to the rack using three rack
mounting screws on each side of the shelf.
Note:
If hole alignment does not permit three screws on each side, it is acceptable to secure the shelf
with only two screws on each side.
13
If the shelf came without the DCM units already installed:
a.
Locate the appropriate units to be installed and remove them from their protective ESD
packaging.
b.
Loosen the thumbscrews and remove the faceplate/cover from the shelf.
c.
Carefully slide each DCM unit into the appropriate shelf slot.
d.
Replace the cover and tighten the thumbscrews to secure each unit in the shelf.
This procedure is complete.
Figure 3-47: Flange Mounted on Right Side of SFD5 Shelf (23-Inch Rack Installation)
m1
65
6s
y_3
Revision 1, June 2009
Содержание FLASHWAVE 7500
Страница 8: ...Revision 1 June 2009 ...
Страница 10: ...Revision 1 June 2009 ...
Страница 16: ...Revision 1 June 2009 ...
Страница 362: ...Revision 1 June 2009 ...
Страница 386: ...Revision 1 June 2009 ...