7.
PLACEMENT AND INSTALLATION
7.1.
If using VPL with the optional Top Landing Gate, proceed to SECTION 9 prior to placing and installing VPL.
7.2.
Position the VPL in its approximate final position.
7.3.
Plug VPL into AC power, reinsert key into the keyed power switch, and turn to the
‘
Power
On’
position.
7.4.
Run the VPL Platform up to the upper landing height. If supplied, use the optional Call/Send Control or
optional Wireless Remote to operate VPL.
Do not operate an occupied VPL that has not been properly anchored to a reinforced concrete pad.
7.5.
Check for adequate running clearances. The platform must be able to travel up/down and the guard ramp
must be able to fold/unfold without interference or obstruction.
7.6.
Shim VPL legs as needed to fine-tune level and plumb.
There is a one-degree (1°) preload angle built into the VPL platform. Level the VPL using the tower as
plumb reference not the platform surface.
If using with a Top Landing Gate, it is recommended that the VPL not be shimmed or anchored until
the Top Landing Gate has been completely installed.
7.7.
Anchor the VPL using four 1/2” x 3
-
1/2” Red Head® Trubolt® Wedge or T Seismic Wedge concrete
anchors or equivalent (not supplied). Follow
the anchor manufacturer’s instructions for proper installation
of concrete anchors.
Ensure anchor tops do not interfere with platform operation.
7.7.1.
The legs of the VPL are pre-
drilled with four 5/8” holes (40” on
-center and 27-
1/8” on
-center)
for anchoring the VPL to a reinforced concrete pad. See FIG. 7.1 for leg anchor layout.
The anchor hole pattern shown below pattern is correct for all standard VPLs.
See Technical Specifications for additional dimensions and anchoring information.
7.7.2.
Once properly anchored and braced (if equipped), the VPL can be operated safely while
occupied for the remainder of the installation.
FIG. 7.1
7.8.
The lower travel limit of the VPL is factory set and should not require adjustment.
7.9.
Upper travel limit adjustment is factory set at the maximum height. Raise the VPL platform until the
platform stops and the ENTER/EXIT indicator illuminates.
7.10.
Measure the vertical distance from the platform deck to the upper landing and record this dimension.
7.11.
Lower the VPL past the upper landing.
Содержание Passport PL44SP3651
Страница 27: ...Page 27 FIG 9 1 FIG 9 2 ...
Страница 65: ...Page 65 23 ELECTRICAL DRAWING ...
Страница 66: ...Page 66 WIRING DIAGRAM 44 52 72 120 144 AND 168 PASSPORT LIFT ...