Commissioning
EngyVolt RV15
20
6
Commissioning
6.1
Post-installation check and switching on the device
Perform all the final checks before commissioning the device.
• Checklist for "post-installation check" (
• Checklist for "post-connection check" (
When the operating voltage is applied, a number of screens are first displayed by way of a self-test
(
If you are commissioning the device for the first time, program the setup as described in the following
sections. If you are commissioning a device that is already configured, the device starts measuring
immediately as defined in the settings and the values are shown on the display.
6.2
Menu structure
First level
Second level
Third level
CHNG PASS
Change password
NPWd
(new password)
Change the value of the password.
Range for selection: 0 to 9
999
Main menu
Password entry
SYS (system configuration)
Choose from:
• 1P2W (single-phase, 2-wire)
• 3P3W (3-phase, 3-wire)
• 3P4W (3-phase, 4-wire)
CT (current transformer primary value) Change the value. Range for selection:
1 to 9
999 A
dIT (integration time of average values
for maximum indicator function)
Choose from:
• 60 minutes
• 30 minutes
• 20 minutes
• 15 minutes
• 10 minutes
• 8 minutes
• 5 minutes
• OFF
RSET (reset)
Choose from:
• dmd (maximum time-integrated
average values - maximum indicator
function)
• ALL
• hour (kWh & kvarh)
COMS (communication)
FMT (protocol)
Choose from:
• Modb (Modbus RTU)
• N2 (Johnson Controls Metasys N2)
bAUd (baud rate)
Choose from:
• 2
400
• 4
800
• 9
600
• 19
200
• 38
400
PARI (parity)
Choose from:
• None
• Odd
• Even
STOP (stop bits)
Choose from:
• 1
• 2
Содержание EngyVolt RV15
Страница 2: ......
Страница 6: ...Safety instructions EngyVolt RV15 6 Reference to a page in this manual Reference to a graphic ...
Страница 62: ......
Страница 63: ......
Страница 64: ...www endress com worldwide BA01040K 09 EN 01 11 71155512 EH COSIMA ...