Eaton 93PM-L 20–200kW (208V) UPS Installation and Operation Manual 164000724—Rev 01
75
Figure 17. UPS Base Strap Install Location
BASE STRAP
INSTALL
LOCATION
27. Install the Deadfront Top Brace removed from the Wireway’s left Front Post in
to the upper
cabinet area, see
for installation location.
Figure 18. UPS Deadfront Top Brace Install Location
DEADFRONT
TOP BRACE
LOCATION
28. If permanently mounting the UPS using the customer supplied left and right side floor mounting brackets,
proceed to
; if using the front and rear floor mounting brackets, proceed to
; otherwise,
proceed to
29. Locate the customer supplied left and right side floor mounting brackets and hardware.
Содержание 93PM-L IAC-B
Страница 1: ...p n 164000724 Revision 01 20 200 kW 208V UPS Installation and Operation Manual Eaton 93PM L UPS ...
Страница 10: ...x Eaton 93PM L 20 200kW 208V UPS Installation and Operation Manual 164000724 Rev 01 List of Tables ...
Страница 112: ...102 Eaton 93PM L 20 200kW 208V UPS Installation and Operation Manual 164000724 Rev 01 UPS System Installation ...
Страница 148: ...138 Eaton 93PM L 20 200kW 208V UPS Installation and Operation Manual 164000724 Rev 01 Communication ...
Страница 154: ...144 Eaton 93PM L 20 200kW 208V UPS Installation and Operation Manual 164000724 Rev 01 UPS Maintenance ...
Страница 158: ...148 Eaton 93PM L 20 200kW 208V UPS Installation and Operation Manual 164000724 Rev 01 Product Specifications ...
Страница 161: ...Eaton 93PM L 20 200kW 208V UPS Installation and Operation Manual 164000724 Rev 01 151 Warranty ...
Страница 162: ...16400072401 164000724 01 ...