Troubleshooting
If you experience difficulties with the EarthLinked
®
system, please review the appropriate section of
the manual. It may be helpful to have another professional HVAC or refrigeration service person
review and check it with you.
Time and expense can be saved by taking a thoughtful and orderly approach to troubleshooting.
Start with a visual check: Are there loose wires, crimped tubing, missing parts, etc?
1) Compressor
After s
etting the remote (wall) thermostat system switch to the “OFF” position and the thermostat fan
switch to the “AUTO” position, proceed to check the supply voltage at (1) the line terminals to the
breaker/disconnect; 2) the system side of the breaker/disconnect, and 3) the line-side of the
transformer. Verify the proper voltage rating for the system. Reference Figure 33.
CAUTION!
SERVICE MAY BE PERFORMED ONLY BY AN EARTHLINKED
TECHNOLOGIES AUTHORIZED PROFESSIONAL HVAC OR
REFRIGERATION SERVICE PERSON. USE ONLY SAFE AND
APPROVED SERVICE TECHNIQUES.
IMPROPER INSTALLATION, ADJUSTMENT, ALTERATION,
MAINTENANCE OR SERVICE CAN CAUSE 1) THE
EARTHLINKED
®
SYSTEM OR COMPONENTS TO MALFUNCTION
AND OR FAIL, 2) PROPERTY DAMAGE, INJURY OR DEATH.
IMPORTANT!
EarthLinked® Refrigerant System Safety Switches
EarthLinked® compressor units are equipped with the following three
safety switches that will turn the compressor off if the following limits
are exceeded.
High Pressure Switch:
Located between the compressor discharge port and
the reversing valve, the
cut-out pressure is 600 psig.
This is a manual reset
switch.
Low Pressure Switch:
Located between the ACC and the compressor
suction port, the
cut-out pressure is 25 psig.
This is an automatic reset
switch.
Discharge Temperature Switch:
Located at the compressor discharge, the
cut-out temperature is 240°F.
This is a manual reset switch.
Содержание Prime-025
Страница 15: ...PSD QS 02 16 Page 15 Figure 8 PSD Compressor Unit Electrical Schematic 230 1 60...
Страница 16: ...PSD QS 02 16 Page 16 Figure 9 PSD Compressor Unit Electrical Schematic 230 3 60...
Страница 17: ...PSD QS 02 16 Page 17 Figure 10 PSD Air Heating Cooling Water Heating Application...
Страница 18: ...PSD QS 02 16 Page 18 Figure 11 PSD Air Heating CoolingWater Heating Field Wiring Diagram...
Страница 20: ...PSD QS 02 16 Page 20 Figure 11a SureStart Mode of Operation...
Страница 27: ...PSD QS 02 16 Page 27 Figure 15 Disassembled Plug Connector...
Страница 34: ...PSD QS 02 16 Page 34 Figure 24 PSD Internal Flow Schematic...
Страница 35: ...PSD QS 02 16 Page 35 Figure 25 PSD Piping...
Страница 37: ...PSD QS 02 16 Page 37 Figure 26 Evacuation of PSD System...
Страница 39: ...PSD QS 02 16 Page 39 Figure 27 Initial Charge of PSD System...
Страница 41: ...PSD QS 02 16 Page 41 Figure 28 Final Charge of PSD System...
Страница 42: ...PSD QS 02 16 Page 42 Figure 29 Charging to the Middle Sight Glass Figure 30 Charging to the Top Sight Glass...
Страница 44: ...PSD QS 02 16 Page 44 Figure 32 Start Up Process...
Страница 53: ...PSD QS 02 16 Page 53...
Страница 54: ...PSD QS 02 16 Page 54...
Страница 55: ...PSD QS 02 16 Page 55...
Страница 56: ...PSD QS 02 16 Page 56...
Страница 57: ...PSD QS 02 16 Page 57...
Страница 58: ...PSD QS 02 16 Page 58...