Earth Loop Protection System
1) Anode Wire Installation
Prior to this, the below grade installation of the DIRECT AXXESS® Earth Loop System, including the
Earth Loop Protection System anode and anode wire has been completed per the
Earth Loop
Protection Kit Manual
, and at this point the anode wire is ready to be connected to the compressor
unit.
The earth loop protection system connection to the anode wire is on the back side of the compressor
cabinet as illustrated in Figure 14, showing the electrical
socket
with the
sealing cap.
Figure 14. Compressor Cabinet Socket/Cap
The EPS-KIT contains the plug connector, which will be field assembled and connected to the
anode wire.
The steps to install the
anode wire
to the
plug connector assembly
are as follows.
Remove the
sealing cap assembly tool
from the compressor unit cabinet shown in Figures 14 and
15. Using the
sealing cap assembly tool,
as shown in Figure 15, unscrew the
locking ring
from the
plug connector assembly
to access the
plug insert.
Then, remove the
gland nut, gland cage,
and gland
from the other end of the
plug body
as shown in Figure 15.
WARNING!
All power of the EarthLinked
®
System is to be shut OFF at the disconnect while
field wiring the Earth Loop Protection System. Failure to do so may result in
serious injury or death, or equipment or property damage.
Содержание Prime-025
Страница 15: ...PSD QS 02 16 Page 15 Figure 8 PSD Compressor Unit Electrical Schematic 230 1 60...
Страница 16: ...PSD QS 02 16 Page 16 Figure 9 PSD Compressor Unit Electrical Schematic 230 3 60...
Страница 17: ...PSD QS 02 16 Page 17 Figure 10 PSD Air Heating Cooling Water Heating Application...
Страница 18: ...PSD QS 02 16 Page 18 Figure 11 PSD Air Heating CoolingWater Heating Field Wiring Diagram...
Страница 20: ...PSD QS 02 16 Page 20 Figure 11a SureStart Mode of Operation...
Страница 27: ...PSD QS 02 16 Page 27 Figure 15 Disassembled Plug Connector...
Страница 34: ...PSD QS 02 16 Page 34 Figure 24 PSD Internal Flow Schematic...
Страница 35: ...PSD QS 02 16 Page 35 Figure 25 PSD Piping...
Страница 37: ...PSD QS 02 16 Page 37 Figure 26 Evacuation of PSD System...
Страница 39: ...PSD QS 02 16 Page 39 Figure 27 Initial Charge of PSD System...
Страница 41: ...PSD QS 02 16 Page 41 Figure 28 Final Charge of PSD System...
Страница 42: ...PSD QS 02 16 Page 42 Figure 29 Charging to the Middle Sight Glass Figure 30 Charging to the Top Sight Glass...
Страница 44: ...PSD QS 02 16 Page 44 Figure 32 Start Up Process...
Страница 53: ...PSD QS 02 16 Page 53...
Страница 54: ...PSD QS 02 16 Page 54...
Страница 55: ...PSD QS 02 16 Page 55...
Страница 56: ...PSD QS 02 16 Page 56...
Страница 57: ...PSD QS 02 16 Page 57...
Страница 58: ...PSD QS 02 16 Page 58...