D 43
6.5
Commissioning and checking the
heater
A
In order to reach the required tempera-
ture, the heater should be switched on
approx. 15 - 20 minutes before the start
of paving.
- Switch on the paver finisher's engine.
- Switch on heating system ON / OFF
switch (74) (
o
)
.
- Switch on the control and monitoring
unit ON / OFF switch (105).
- Switch on the electrically heatable
side shields' (
o
) ON / OFF switch
(83).
The heating system is activated and the
heating process begins.
During the heating process, the individu-
al screed section heaters' indicator
lamps (79-81) and the status displays
(109) of the control and monitoring unit
light up.
Once the set temperature has been
reached, the indicator lamps go out one
after another.
Once all screed parts have reached the
desired temperature, paving operation
may begin.
If additional heating occurs during pav-
ing operation, this is indicated by the in-
dicator lamps (79-81).
A
The heater indicator lamps (109) in the
control and monitoring unit can addition-
ally be monitored.
3
74
79
4
105
109
80 81 82
Содержание V5100TV-H
Страница 2: ...www dynapac com...
Страница 10: ...V 2...
Страница 24: ...A 2...
Страница 35: ...B 11 5 o 4 7 2 1 6 2 4 o 1 3...
Страница 42: ...C 4 2 1 4 3...
Страница 57: ...D 15 4 Screed heater conventional version 4 1 Switch cabinet for screed heater 30 31 32 35 36 34 33...
Страница 63: ...D 21 5 Screed heater PLC version 5 1 Switch cabinet for screed heater 40 43 44 42 41...
Страница 65: ...D 23 5 2 Operating the control and monitoring unit 45 46 55 47 48 49 50 53 54 51 52...
Страница 78: ...D 36 6 2 Operating the control and monitoring unit 100 101 110 102 103 104 105 108 109 106 107...
Страница 94: ...D 52...
Страница 100: ...E 6 Transport position 5 4 6 9 12 10 11 14 15 15 14 13...
Страница 128: ...E 34 6 6 Material guide plate brace 1 2 3 3 4 6 5 7 9 8 10 11 II I 4...
Страница 136: ...E 42...
Страница 144: ...F 8 5 2 Guide tubes 1 1 2 2 2x 1 2...
Страница 148: ...F 12 6 2 Cleaning the screed Emptying the tamper compartment 1 1 2 2 2a 1a 1a 3 4 3 4...
Страница 154: ...F 18 8 Gas system The gas system consists of the following main components Ignition burner 1 Spark plug 2 1 2...
Страница 163: ...F 27 14 2 PLC version gas heater Fuses in the switch cabinet of the screed heater A Fuses A...
Страница 166: ...F 30 Fuses in the control unit of the screed heater Fuses B B Fuses F A F10 Heater control system 1 F11 Heater OFF 3 B...
Страница 168: ...F 32 Fuses in the control unit of the screed heater Fuses B B Fuses F A F10 Heater control system 1 F11 Heater OFF 3 B...
Страница 194: ...G 22...
Страница 196: ...www dynapac com...