12
|
Commissioning
Installer reference guide
245
ERLA11~W1 + EBVH16SU23DJ
Daikin Altherma 3 R F
4P655196-1 – 2021.09
The
fuses
or locally installed protection devices are installed according to this document,
and have NOT been bypassed.
The
power supply voltage
matches the voltage on the identification label of the unit.
There are NO
loose connections
or damaged electrical components in the switch box.
There are NO
damaged components
or
squeezed pipes
on the inside of the indoor and
outdoor units.
Backup heater circuit breaker
F1B (field supply) is turned ON.
There are NO
refrigerant leaks
.
The
refrigerant pipes
(gas and liquid) are thermally insulated.
The correct pipe size is installed and the
pipes
are properly insulated.
There is NO
water leak
inside the indoor unit.
The
shut-off valves
are properly installed and fully open.
The
stop valves
(gas and liquid) on the outdoor unit are fully open.
The
air purge
valve is open (at least 2 turns).
The
pressure relief valve
purges water when opened. Clean water MUST come out.
The
minimum water volume
is guaranteed in all conditions. See "To check the water
volume and flow rate" in
104].
The
domestic hot water tank
is filled completely.
12.4 Checklist during commissioning
The
minimum flow rate
during backup heater/defrost operation is guaranteed in all
conditions. See "To check the water volume and flow rate" in
104].
To perform an
air purge
.
To perform a
test run
.
To perform an
actuator test run
.
Underfloor screed dryout function
The underfloor screed dryout function is started (if necessary).
12.4.1 Minimum flow rate
Purpose
For a correct operating unit, it is important to check if the minimum flow rate is
reached. If needed, modify the bypass valve setting.
If operation is…
Then the minimum required flow rate
is…
Heating/defrost
22 l/min
Domestic hot water production