Mounting and Operating Manual
Central Battery System EURO ZB.1
46
CEAG Notlichtsysteme GmbH
Connection in control cabinet EURO
ZB.1 (EURO US.1) is effected on a con-
trol unit ST 20 E terminal block (S3 / S4)
for external connections (Fig. 8, Item 3).
Notes:
If several subdistributors
have to be monitored, additional
devices must be hooked up and
connected to the other devices in
a 24-V loop (see Fig. 38).
If less than 3 phases have to
be monitored by one 3-phase
monitoring unit, the remaining
inputs of the 3-phase monitoring
unit must be bridged.
These devices are of slide-on built-in
type for mounting in a control cabinet/
subdistributor.
They are fixed to a 35-mm carrier rail
according to DIN EN 50 022.
Mount the device onto the carrier rail
at the desired location.
Carefully snap the device in place.
Connecting leads are wired to the
screw terminals on the device (see
Fig. 36 and single-line diagrams be-
low).
Fig. 36:
CEAG 3-phase monitor
Mounting and Connection of a CEAG 3-phase monitor
with 24 V loop
11.11
Mounting and Connection of a CEAG 3-phase
monitor with 24 V loop
Fig. 38: Single-line diagram showing
connection of several CEAG 3-phase
monitoring units
Fig.37: Single-line diagram of CEAG
3-phase monitoring with 24 V control
loop for safety light requests
Emergency lighting
General lighting
Emergency lighting