Start-up sequence
Unit power supply ON
Yes / No
1 Compressor carter resistances operating at least since 8 hours
2 Off-load voltage measure
3 Phase sequence check
4 Pump manual start-up and flow check
5 refrigeration circuit shut-off valves opening (if applicable)
6 Unit ON
7 load voltage measure
8
If remote On-Off:
set dip-switch S5-3 on ON
9
If units in modular configuration
set dip-switch S12-2 on ON
10 Verify the lack of bubbles in the liquid light (if applicable)
11 Check of all fan operating
12 Measure of return and supply water temperature
13 Super-heating and sub-cooling measure
14 Check no anomalous vibrations are present
15 Set-point personalization
16 scheduling customisation
17 Complete and available unit documentation
Содержание WSAT-YES FC
Страница 1: ...M0NC00002 00 12 20 WSAT YSi...
Страница 2: ...Cool Antifreeze heater Signals Remote On Off Rapid guide CN33 CN24...
Страница 20: ...1 Piping inlet outlet side 2 Electrical panel side 3 Anchoring bolts Size 16 2 24 2 Size 30 2 40 2 1 2 3...
Страница 26: ...Storage tank Option Vent Drain On Off Inverter pump Option...
Страница 34: ...UNITA IN CONFIGURAZIONE MODULARE...
Страница 85: ...85...
Страница 86: ...Via Camp Lonc 25 Z I Villapaiera 32032 Feltre BL Italy Tel 39 0439 3131 Fax 39 0439 313300 info clivet it...