Step 3:
Step 4:
Step 5:
Step 6:
Step 7:
Remove the riser's side access panel. Use the Torx tool from the installation kit to remove the (6) Allen bolts.
Using a suitable lifting device (with its slings attached to the cabinet lifting eyebolts), lift the cabinet two feet
above the ground. Position the suspended cabinet directly above the riser, with the two battery compartment
door openings aligned on the same side.
Slowly lower the cabinet onto the riser, keeping the (4) anchor holes in the cabinet base aligned with the coun-
terpart holes in the riser.
Attach the cabinet base to the riser using (4) anchor bolts, (8) square washers, (4) lock washers, and (4) nuts
(one set per each of the four anchor holes).
Tighten all hardware to secure the cabinet to the riser.
If you are using the battery compartment riser to house a second string of batteries, perform the additional steps below to
connect the second-string battery cables to the cabinet power system. If you are only using the riser as a pedestal, skip the
remaining task.
To connect the battery cables to the cabinet power system
Feed the second-string battery power
cables from the riser into the cabinet’s
battery compartment through the hole on
the left side.
Feed the cables from the battery
compartment into the equipment
chamber through the vacant hole (and
grommet) on the left side.
Route the cables up the rack to the rear
of the optional Valere power shelf.
Connect the cable lugs to battery breaker
position #2 on the rear of the optional
Valere shelf, as shown.
Step 1:
Step 2:
Step 3:
Step 4: