Proprietary Information: Not for use or disclosure except by written agreement with Clearfield.
82
FieldSmart
®
Fiber Active Cabinet (FAC) 3200
Installation Manual
_________________________________________________________
Step 1:
Step 2:
Step 3:
Step 4:
Step 5:
Step 6:
To support 110-120 VAC service, the cabinet AC load center must be re-configured in the field. See
Installing AC Power
(110-120 VAC)
for details. If the cabinet is equipped for 110-120 VAC service, test the AC power supply
voltage as follows.
To check 110-120 VAC power supply voltage
Apply AC power to the cabinet at the local power transfer switch.
At the cabinet AC load center, do the following:
a.
Remove the left and right cover panels from the AC load center.
b.
Switch the 60A Main Service Disconnect breaker to
ON
.
c.
Switch the 60A Main breaker to
ON
.
Using a volt meter, test between the L1 and neutral busses:
a.
Place one lead on the L1 buss.
b.
Place the other lead on the neutral buss.
c.
Verify that the volt meter reads between 110 and 120 VAC.
Using a volt meter, test between the L2 and neutral busses:
a.
Place one lead on the L2 buss.
b.
Place the other lead on the neutral buss.
c.
Verify that the volt meter reads between 110 and 120 VAC
Switch the branch breakers on as follows:
• Switch the 15A Conv. Outlet breaker to
ON
.
• If you are using an optional battery heater, switch the 15A Heater breaker to
ON
.
Note:
Do not switch on the Rectifier A and Rectifier B breakers at this time.
Re-attach the left and right cover panels on the AC load center.