32
Has the Heater been filled with mains water and
the Filling Loop been removed?
Have the Pool water connections been made to
the correct fittings?
CASING PANELS
Have grommets been fitted to relevant oil supply
entry points?
Have the grommet cable entry connections been
used?
BURNER
Is the oil pump by-pass screw fitted, if applica-
ble?
Remove the burner. Is the correct nozzle fitted?
If the burner has an adjustable head, do the set-
tings agree with those given in the Heater instruc-
tions?
Is the Air Shutter adjustment correct?
NOTE:
- Burner operating instructions can conflict be-
cause they are intended for general guidance. Since
the burner has been specifically matched to the par-
ticular Heater, the information in the Heater manual
takes precedence.
FLUE
Is the flue adequately sized for the appliance rat-
ing?
Is the flue free of any obstruction?
Has the chimney been adequately lined and in-
sulated?
NOTE:
- Lining the flue and back filling will help pre-
vent condensate problems.
BALANCED FLUE APPLIANCES
Can leakage from flue tubes or air ducts occur?
VENTILATION
CONVENTIONAL FLUED HEATERS
Is the ventilation opening from the outside to the
Heater room adequate?
Is there sufficient clearance for air to enter the Air
Entry Plates on side or rear of appliance?
Will any ventilation fans prevent adequate supply
of combustion air?
ELECTRICAL POWER SUPPLY
Is the electrical supply to the appliance appropri-
ate?
Are the electrical input connections to the control
panel correct?
Are the electrical connections from the Heater
control panel to the burner correct?
Is the supply fuse correct?
Does the wiring comply with the latest IEE Regu-
lations?
Does the power supply cable enter the casing
through an air tight cable grip?
GENERAL
Has the Heater been installed in accordance with
manufacturers instructions?
7:8 RECOMMENDED
COMMISSIONING TESTS
Have the manufacturers on-site assembly instruc-
tions been followed?
COMMISSIONING TESTS
BEFORE ATTEMPTING TO START THE HEATER
PLEASE THOROUGHLY CHECK ALL ITEMS ON
THE COMMISSIONING CHECK LIST. THIS WILL
HELP TO AVOID UNNECESSARY CALL BACKS
Fill Heater following the steps detailed in 7:2.
With the plug for the burner NOT fitted, turn on
electricity supply and by using the switch on the
Pool Thermostat Control, run the internal pump
in short bursts to bleed the air from the Manual
Air Vents.
When running quitely, turn off and reconnect the
burner.
Fit combined air bleed manifold and 0-300 psi (0-
20 bar) pressure gauge to the appropriate oil
pump connection, and replace burner.
Set the Heater Pool Thermostat Control to above
the actual temperature.
9-04-02
Содержание COH110
Страница 60: ...14 Fig 4 9b Reillo bypass adjustment 9 04 02 Fig 4 9a Reillo bypass adjustment ...
Страница 63: ...17 9 04 02 ...
Страница 82: ...36 9 04 02 ...
Страница 83: ...37 Model 220 only Fig 8 3c Model 280 only Fig 8 3d Top Top Top 9 04 02 ...
Страница 86: ...40 9 3 BURNER PARTS 9 04 02 Model 110 443T58 ...
Страница 87: ...41 29 01 08 Model 180 459T55 3007708 ...
Страница 88: ...42 29 01 08 Model 220 464T55 3007708 ...
Страница 96: ...Station Lane Industrial Estate Witney Oxon Tel 01993 778855 Fax 01993 703407 Booklet 12 M3491 7 11 02 ...