Conveyor Setup and Adjustment:
For initial conveyor setup refer back to the layout drawing for approximate dimensions. Once the
BBL is in the final Position then take a chalk line and make a line parallel with the BB filler structure
and align the conveyors off that line. Then maintain the following:
For the initial setup make sure the powered discharge conveyors are at equal heights
(in feed and out feed). Also, they must of equal height to the receiving end of the
gravity roller conveyor.
Maintain a minimum clearance of a 1/2" between the bulk bag filler discharge conveyor
and the 2nd conveyor to be sure you don't influence your scale weighing.
A. Maintenance:
Check Live Chain Roller (LRC) once a year and remove slack in the chains as required.
Check oil levels on gear boxes once a year.
B. Installation and Maintenance of Speed Reducers and Drives
This manual provides information concerning usage, lubrication, and maintenance of the
Speed Reducers. To maximize the life and efficiency of your reducers follow these
instructions on a regular basis.
***************
To determine the ratio and/or the assembly date of the reducer refer to the numbers
stamped on the end of the output shaft.
If properly used, the reducer should require little maintenance except for scheduled
lubrication.
Initial Oil Change: Drain the oil in a new Speed Reducer after approximately 500 hours of
operation and refill with recommended oil from lubrication chart.
Содержание 520
Страница 1: ...1 CBE 520 BULK BAGGER Safety Installation Operation Maintenance ...
Страница 10: ...10 CHAPTER 1 General Information ...
Страница 14: ...14 CHAPTER 2 INSTALLATION GUIDE ...
Страница 18: ...18 CHAPTER 3 LOAD CELL WIRING ...
Страница 22: ...22 Figure 3 500 Series Bottom View ...
Страница 23: ...23 CHAPTER 4 COMPONENT DESCRIPTION ...
Страница 26: ...26 CBE DENSIFYING DECK ...
Страница 27: ...27 CHAPTER 5 OPERATIONAL SEQUENCE ...
Страница 33: ...33 CHAPTER 6 Conveyors Setup ...
Страница 38: ...38 CHAPTER 7 PLC and Timers and Adjustments ...
Страница 43: ...43 CHAPTER 8 WEIGH CONTROLLER And ADJUSTMENTS ...
Страница 45: ...45 ...
Страница 48: ...48 See attached Documentation For the Controller specifically Used on your machine ...
Страница 49: ...49 Chapter 9 MAINTENANCE ...
Страница 51: ...51 CHAPTER 10 TROUBLESHOOTING ...
Страница 55: ...55 ...
Страница 56: ...56 CHAPTER 11 STANDARD ILUSTRATED PARTS See attached documentation for Other parts Specific to Your Bagger ...
Страница 57: ...57 CHAPTER 12 PLC and TIMER ADJUSTMENTS ...
Страница 61: ...61 DRAWINGS AND SCHEMATICS See attached Schematics And Drawings specific for your machine ...