3. Installation instructions:
With the applicator properly installed on the robot, the functions of the unit can be tested. First, open the
air supply. There must be no sound from leaking air.
Check that the solenoid valves are working properly by open and closing each valve from the robot
pendant and listen to the sound of the piston in operation.
Apply material supply pressure and check for leakage.
Move the applicator to the purge position and purge all nozzles one by one until the unit is filled up with
material and all entrapped air is removed from the supply system.
Open the circulation valve and purge the material through the dump valve until all entrapped air in the
material return is removed.