6
Initial operation
Logano plus SB615 Gas - We reserve the right to make any changes due to technical modifications.
36
6.3
Preparing the heating system for
operation
Observe the following when commissioning:
B
Before commissioning, bleed the heating system via
the venting facility provided for this purpose.
B
Check that the inspection opening of the flue gas
collector is closed (
Æ
Fig. 32, page 42).
B
Ensure that the burner door is secured with door bolts.
B
Check that the safety equipment is functioning
properly.
6.4
Commissioning the control unit and
the burner
B
Use the control unit to start the boiler.
By commissioning the control unit, you also automatically
commission the burner. The burner can then be started via
the control unit. For further details, see the installation
instructions of the relevant control unit or burner.
B
Complete the commissioning report in the technical
burner documentation.